Storage Period
1 - 3 storage years (1.4.2025 - 1.4.2028)
Working Gas Volume
440 000 MWh
Injection Output
4 478 MWh/day
Withdrawal Output
7 371 MWh/day
There was a planned shutdown at Uhřice USF between 11 September and 24 September 2022.
During the shutdown, a record 16 reinforcements were replaced at Uhřice USF and at MS Brumovice.
At the same time, new safety reinforcements were installed at the USF probe collector, improving operating safety and reliability (see the photo)
All the planned servicing and repair work was completed on time, and the equipment is ready to meet the requirements of our customers.